Alpine-Balsam Costs

Itemyeartotal budgettotal obliGATIONstype of expense
Campus Purchase
2015

$41,560,000

$40,212,000

Debt Expenses
Anticipated Total Land Certificates of Participation (COP) Interest2015

$18,200,000

$18,200,000

Debt Expenses
Early Planning - Vision Plan, Area Plan, Assessments and Studies
2016-2021

$702,723

$702,000

Completed (Actual) Expenses
Vision Plan
2016-2017

$252,000

Completed (Actual) Expenses
Area Plan Costs
2018-2019

$254,000

Completed (Actual) Expenses
Form-Based Code
2020-2021

$28,000

Completed (Actual) Expenses
Other Assessments / Studies
2016-2021

$168,000

Completed (Actual) Expenses
Western City Campus - Brenton Renovation
2017-2018

$8,131,100

$8,010,000

Completed (Actual) Expenses
Construction costs

$5,600,000

Completed (Actual) Expenses
Design + Engineering services

$2,400,000

Completed (Actual) Expenses
Environmental Assessments

$10,000

Completed (Actual) Expenses
Hospital Decommissioning & Deconstruction
2018-2022

$19,755,165

$19,429,000

Completed (Actual) Expenses
Operating Costs (security, utilities, snow removal, landscape maintenance, etc.)

$818,000

Completed (Actual) Expenses
Environmental Assessments

$99,000

Completed (Actual) Expenses
Decommissioning, Technical Energy Audit phase, & Other (Groundwater, Xcel, Lumen, hazmat assessments, legal)

$744,000

Completed (Actual) Expenses
Interior Deconstruction

$8,326,000

Completed (Actual) Expenses
Exterior Deconstruction

$9,442,000

Completed (Actual) Expenses
Alpine-Balsam Site Prep and Western City Campus - Current Projects

$174,900,032

$174,900,000

Active (Encumbered) Expenses
New City Services and Staffing Hub (former Medical Pavilion)
2022-Present
See budget total above

$142,967,000

Active (Encumbered) Expenses
Construction costs - $100,000,000 financed through COPs/debt and $17,000,000 from current city revenue

$117,000,000

Active (Encumbered) Expenses
Furniture, Fixtures & Equipment

$5,500,000

Active (Encumbered) Expenses
Design + Engineering (Includes New City Building, Parking Structure, Site Infrastructure)

$17,742,000

Active (Encumbered) Expenses
Tasks: 3rd party testing (Ground, Xcel, Lumen, hazmat assessments, legal support)

$1,404,000

Active (Encumbered) Expenses
Soils & Groundwater

$169,000

Active (Encumbered) Expenses
Public Art ($1M + BCH Decon carryover)

$1,152,000

Active (Encumbered) Expenses
Parking Structure
2016-Present
See budget total above

$14,321,000

Active (Encumbered) Expenses
Construction costs

$13,700,000

Active (Encumbered) Expenses
Structural repairs (completed in 2016)

$384,000

Completed (Actual) Expenses
Lighting improvements (completed in 2016)

$237,000

Completed (Actual) Expenses
Site Infrastructure (floodway, utilities, streets, etc.) - these projects support both the WCC and future housing units2020-Present
See budget total above

$17,612,000

Active (Encumbered) Expenses
Floodway Construction

$16,000,000

Active (Encumbered) Expenses
Design + Engineering (primarily floodway, other engineering included under new building)

$1,335,000

Active (Encumbered) Expenses
Tasks (underground, Xcel, Lumen, etc.)

$277,000

Active (Encumbered) Expenses
Anticipated Total Building COP Interest

$90,400,000

$90,400,000

Debt Expenses
Affordable Housing Units - City Investments2023-2028 (fund expenditure timeline); first set of units built by 2028; second set of units built by 2030

$14,503,000

$14,503,000

Completed (Actual) Expenses plus Anticipated Spend
TOTAL ANTICIPATED EXPENSES (Including future COP Payments)

$368,152,020

$366,356,000

TOTAL EXPENSES (Excluding COP Interest Payments)

$257,756,000