Large industrial or manufacturing campuses where multiple buildings are served by a central plant or single utility meter will be subject to the following custom requirements.
Lighting Upgrade Requirements:
Deadlines
The large industrial campus deadlines are below.
REQUIREMENT | DEADLINE |
---|
Rating and Reporting | June 1, 2016 |
Energy Assessment | June 1, 2019 |
Implement Cost-Effective Measures | June 1, 2021 |
Lighting Upgrades | June 1, 2025 |
Calculate Percentage of Total Energy Savings
To calculate the percentage of total energy savings for the purpose of developing a plan, follow the steps below:
- Calculate/measure the calendar year energy savings* in electricity consumption = X1 kWh
- Calculate/measure the calendar year energy savings* in fuel (oil & gas) consumption = Y1 MMBtu
- Get the total actual calendar year electricity consumption = X2 kWh
- Get the total actual calendar year fuel consumption = Y2 MMBtu
- Get the total actual calendar year energy cost = A $K
- Get the total actual calendar year electricity cost = B $K
- Get the total actual calendar year fuel cost = C $K
The energy savings as a percent of the total energy (electricity and fuel) consumption for "xxxx" year is calculated by the following formula:
{(B/A) * (X1)/X2 + (C/A) * (Y1/Y2)} * 100 = Percent Energy Conservation for the Year
* The energy savings from a project can be counted for 12 months. For example, a project saving 12,000 kWh annually (1,000 kWH/month) that is implemented on Nov. 1, 2015 would have 2,000 kWH in 2015 and 10,000 kWH of "carryover" savings in 2016.
** This calculation can be annualized over four years to account for significant investments and savings that may have been made in prior years.
Exemptions
Owners of large industrial campuses may be exempt from the energy assessment and lighting upgrade requirements if:
- The owner submits proof acceptable to the city manager demonstrating that energy efficiency measures or on-site renewable energy sources produced a reduction of total energy usage of at least two and a half percent, annualized over four years; or
- If in the opinion of the city manager, the large industrial campus has established an energy or emission reduction goal that is equivalent to that established by the city and the large industrial campus is making adequate progress toward that goal after at least two years of compliance with the rating and reporting requirement outlined above.
If you think your campus qualifies for an exemption, contact the Program Administrator.