Active Construction and Maintenance

Find up-to-date information on construction and maintenance impacts occurring throughout the city.

City Facility Impacts

City FacilityClosure Impact
11th & Spruce Parking Garage
  • Week of June 1: Full Garage Closure – Parking Garage Closed 4 Months
  • Week of June 15: Construction Begins on Tenant Spaces (Details for Each Space will be provided)
  • July 29: A crane will be used to remove and replace rooftop heating and air conditioning equipment, requiring temporary lane and sidewalk closures from 7 a.m. to 5 p.m. One lane of Spruce Street between Broadway and 11th Street and one lane of 11th Street between Spruce Street and Morrison Alley will be closed. Sidewalks adjacent to the 11th & Spruce Garage will also be temporarily closed, with staff on site to help direct pedestrians safely around the work area. Businesses and visitors should expect increased construction activity and traffic in the area during the day. These temporary closures are necessary to safely complete this critical phase of the project.
Alpine Balsam Site
  • Now - Aug. 5: east end of Alpine Ave. expected to remain closed to allow for continued work between the garage and new office.
  • Now - Sept. 30: southbound Broadway sidewalk between Balsam Ave. and Alpine Ave. is closed.
North Boulder Recreation Center
  • Aug. 1 - tentatively scheduled to reopen early October: Lab Pool and Hot Tub
  • Aug. 8 - tentatively scheduled to reopen in September: Leisure Pool and Sauna
  • Aug. 15 - Aug. 23: Planned, annual maintenance shutdown.
South Boulder Recreation Center
  • Aug. 29 - Sept. 7: Planned, annual maintenance shutdown.

Why Parking Garage Improvements Are Needed and How the Schedule Was Chosen

The City of Boulder began major improvements to the 1100 Spruce parking garage requiring a full closure of the garage from June 6 to October 2. This work is needed now because key structural components have reached the end of their useful life, and making repairs now will protect the garage, improve safety, prevent more costly damage, and extend the life of the facility. By completing multiple repairs during one construction period, the city can finish the work more efficiently and reduce the need for future closures and disruptions.

Here's some more rationale for the renovation:

Rationale for Summer 2026 Construction Timing

  • The garage is one of the oldest and most heavily used downtown facilities and requires critical repairs in advance of Sundance Film Festival. Proactive work helps mitigate safety risks and avoid disruptions similar to the recent parking garage collapse in Denver, which negatively impacted nearby businesses and property values.
  • Concrete installation requires sustained temperatures of 50°F or higher. Winter construction would introduce significant weather delays or require temporary heating, increasing both costs and project duration.
  • A full garage closure was selected to compress the construction schedule and enhance safety for both the public and construction crews.
  • The project schedule is aligned to minimize impacts on major community events, with full closure planned:
    • After peak spring events (e.g., graduation, Bolder Boulder, Boulder Creek Festival)
    • Before the Sundance Film Festival
  • Timing also avoids overlap with planned work at St. Julien Hotel & Spa in late 2026–early 2027. Coordinating construction is critical, as garage work at the hotel is highly disruptive due to noise and dust, which are not compatible with guest expectations—particularly during peak periods such as Sundance.