Active Construction and Maintenance

Find up-to-date information on construction and maintenance impacts occurring throughout the city.

City Facility Impacts

City FacilityClosure Impact
11th & Spruce Parking Garage
  • June 1 - Oct. 16: Full Closure
Chautauqua Park
  • Now - Nov. 30: Impacts to parking and traveling through the park due to stormwater improvement construction.
  • Oct. 12 - 13: Chautauqua Park Green Loop closure, parking still available west side of loop.
  • Project Details
Foothills Community Park
  • Oct. 12 - Oct. 22: Replacement of sidewalk to north end dog park and trash dumpster pad in south parking lot.
  • Oct. 19 - Oct. 23: North play area impacts, east/lower section surfacing, removal and replacement.
Hawthorn Gardens
  • Oct. 19 - Feb. 2027: Complete irrigation rebuild.
Martin Park
  • Oct. 12 - Oct. 30: Sidewalk repairs and widening.
North Boulder Recreation Center
  • Aug. 1 - tentatively scheduled to reopen Nov. 1: Lab Pool and Hot Tub Closure
Tom Watson Park
  • October: Construction on outer loop path east of tennis courts. Signage will be posted as dates are confirmed.

Why Parking Garage Improvements Are Needed and How the Schedule Was Chosen

The City of Boulder began major improvements to the 1100 Spruce parking garage requiring a full closure of the garage from June 6 to October 2. This work is needed now because key structural components have reached the end of their useful life, and making repairs now will protect the garage, improve safety, prevent more costly damage, and extend the life of the facility. By completing multiple repairs during one construction period, the city can finish the work more efficiently and reduce the need for future closures and disruptions.

Here's some more rationale for the renovation:

Rationale for Summer 2026 Construction Timing

  • The garage is one of the oldest and most heavily used downtown facilities and requires critical repairs in advance of Sundance Film Festival. Proactive work helps mitigate safety risks and avoid disruptions similar to the recent parking garage collapse in Denver, which negatively impacted nearby businesses and property values.
  • Concrete installation requires sustained temperatures of 50°F or higher. Winter construction would introduce significant weather delays or require temporary heating, increasing both costs and project duration.
  • A full garage closure was selected to compress the construction schedule and enhance safety for both the public and construction crews.
  • The project schedule is aligned to minimize impacts on major community events, with full closure planned:
    • After peak spring events (e.g., graduation, Bolder Boulder, Boulder Creek Festival)
    • Before the Sundance Film Festival
  • Timing also avoids overlap with planned work at St. Julien Hotel & Spa in late 2026–early 2027. Coordinating construction is critical, as garage work at the hotel is highly disruptive due to noise and dust, which are not compatible with guest expectations—particularly during peak periods such as Sundance.