Project Overview

Open Space & Mountain Parks (OSMP) is implementing several changes to the western trails of the Boulder Valley Ranch (BVR) area which are outlined in the North Trail Study Area (TSA) Management Plan PDF. The North TSA Plan had significant community input, and was approved by the Open Space Board of Trustees and Boulder City Council in 2016.

The North TSA Plan provides direction for OSMP to implement the following in the western Boulder Valley Ranch area:

  • Improve visitor experience and trail connectivity by replacing high-density low-quality trails with fewer high-quality sustainable trails that minimize impacts to sensitive ecological resources.
  • Improve bike access through conversion of some trails to allow bicycle use.
  • Protect habitat by closing undesignated trails and some sections of designated trails.

Trail Closures

OSMP expects that construction-related trail closures will be minimal during upcoming work, although there may be short, intermittent closures to support construction work in the area. Upcoming closures will be posted below.

Project Updates

Nov. 19, 2024 update: OSMP and Timberline Trailcraft have completed and opened up a half-mile section of the Eagle Trail re-route! This new trail section replaces the steep, loose, and erosive section of Eagle Trail south of Boulder Valley Ranch Trailhead. The new trail is open to hikers, bicycles, and equestrians, and has been designed to accommodate adaptive mountain bikes – hand-pedaled cycles often used by people with disabilities. Please stay on the trail – do not shortcut, and do not utilize trails marked as closed – your efforts will help to protect vegetation and help closed trails to re-vegetate.

Sept 5, 2024 update: Construction of the Eagle Trail re-route is under-way with OSMP’s contractor, Timberline Trailcraft! OSMP crews, volunteers, and Boulder Mountainbike Alliance anticipate starting construction of the Cobalt Trail re-route on Sept 9 – when complete, this trail will allow for bike access.

Trail Changes in the Project Area

  • The section of Eagle Trail between the Sage Trail junction west to the shade shelter will be re-routed with a new 2/3-mile route. This will replace the existing steep and erosive section of trail with a more sustainable and enjoyable trail grade. Trail use will remain open for hikers, mountain bikers, and equestrians. In conjunction with this project, a section of narrow single-track trail adjacent to Sage Trail will be constructed to connect the historic Eagle/Sage Trails junction with the new one.
  • Shale Trail will be constructed from the Boulder Valley Ranch Trailhead to the mesa-top to the southwest (connecting to Eagle Trail). This new 2/3-mile trail will replace two existing undesignated trails in order to reduce impacts to rare Bell’s twinpod plant habitat. This trail will be open to hikers and equestrians only in order to provide a non-bike route to the top of the mesa.
  • Cobalt, Hidden Valley, and Degge Trails will be re-routed to improve trail sustainability and visitor experience. All of these trails will be opened to bicycle use, while retaining historic hiking and equestrian uses.
  • Mesa Reservoir Trail and portions of Degge Trail will be closed to improve habitat conditions around Mesa Reservoir.
Map showing trail changes in the western Boulder Valley Ranch project area

View a larger version of the map.

Project Schedule

Project progress depends on weather conditions and trail system-wide priorities. OSMP estimates the following schedule for implementation of the western BVR area projects:

  • Eagle Trail re-route: Expected to start Wednesday, Sept. 4.
  • Cobalt Trail: Expected to start Monday, Sept. 16.
  • Shale Trail: Spring-Summer 2025
  • Hidden Valley and Degge Trails: 2025
  • Closure of Mesa Reservoir and Degge Trails: 2025

You can help!

Please visit www.volunteerosmp.org to learn more about volunteering on this effort!

Project Benefits

Improving trail condition and sustainability

Re-routing trails to sustainable standards will make them less prone to erosion and other issues. Several trail sections will be surfaced with gravel to alleviate seasonal mud issues. OSMP expects that occasional closures will be necessary during muddy conditions in order to maintain good trail conditions.

Additional bicycle access

Some trails, when re-routed, will allow for mountain bike use, along with historically allowed hiking and equestrian use.

Improving accessibility

OSMP has placed high priority on providing trail experiences for visitors with disabilities. In the western BVR trails complex, trails that are open to mountain bikes will be constructed to also accommodate adaptive mountain bikes – hand-pedal driven bikes used by people with disabilities. Through use of modest trail design changes, these trails can be constructed such that they are available for a broader range of the community to enjoy.

Improved habitat

Undesignated trails (social trails) currently traverse through sensitive habitats, such as areas that are home to the rare Bell’s twinpod – a plant that only exists in a few locations in Boulder and Larimer Counties, and nowhere else in the world! OSMP will close these trails and others that the North TSA Plan has identified for closure to improve vegetation and wildlife habitat.

A group of volunteers from Boulder Mountainbike Alliance working on a trail