Development Review Applications are reviewed at regular intervals of either two or three weeks. Below, we have our review calendars posted, and these dates apply for both new applications and revisions to existing applications. For questions about the Development Review Application process, please reach out to our staff through Inquire Boulder.
Submittal Deadlines
2026 Administrative Review Track Calendar
Case Types: Administrative Reviews (ADR), Revocables (REV), Pre-Applications (PAR)*
All materials due by 10 a.m. on the Wednesday date posted.
*Staff written response date may vary.
| Application Submittal Deadline | Staff Written Response to Applicant |
|---|---|
| Dec. 30, 2025 | Jan. 16 |
| Jan. 14 | Jan. 30 |
| Jan. 28 | Feb. 13 |
| Feb. 11 | Feb. 27 |
| Feb. 25 | March 13 |
| March 11 | March 27 |
| March 25 | April 10 |
| April 8 | April 24 |
| April 22 | May 8 |
| May 6 | May 22 |
| May 20 | June 5 |
| June 3 | June 22* |
| June 17 | July 6* |
| July 1 | July 17 |
| July 15 | July 31 |
| July 29 | Aug. 14 |
| Aug. 12 | Aug. 28 |
| Aug. 26 | Sept. 11 |
| Sept. 9 | Sept. 25 |
| Sept. 23 | Oct. 9 |
| Oct. 7 | Oct. 23 |
| Oct. 21 | Nov. 6 |
| Nov. 4 | Nov. 20 |
| Dec. 2 | Dec. 18 |
2026 Land Use Review Track Calendar
Case Types: Land Use Reviews (LUR), Technical Documents (TEC), Standard Floodplain Development Permits (FLD, requires public process), Wetland Development Permits (WET, requires public process)
All materials due by 10 a.m. on the Wednesday date posted.
* Indicates near a holiday, which may effect deadlines.
| Application Submittal Deadline | Staff Written Response to Applicant |
|---|---|
| Dec. 30, 2025 | Jan. 23 |
| Jan. 21 | Feb. 13 |
| Feb. 11 | March 6 |
| March 4 | March 27 |
| March 25 | April 17 |
| April 15 | May 8 |
| May 6 | May 29 |
| May 27 | June 22* |
| June 17 | July 10 |
| July 8 | July 31 |
| July 29 | Aug. 21 |
| Aug. 19 | Sept. 11 |
| Sept. 9 | Oct. 2 |
| Sept. 30 | Oct. 23 |
| Oct. 21 | Nov. 13 |
| Nov. 10* | Dec. 4 |